Capital Management Report: Quarter 2

Meeting: 05/12/2019 - Cabinet (Item 108)

108 Capital Management Report: Quarter 2 pdf icon PDF 132 KB

To consider and decide on the recommendations as set out in the attached report.

Additional documents:

Decision:

RESOLVED –

  1. That the actual gross and net expenditure for the year and the sources of finance, as shown in Appendices B to D to the report be noted;
  2. That the proposed variations to the 2019/20 Capital programme set out in paragraphs 4.3 to 4.8 of the report be approved;
  3. That the inclusion of new schemes to the Capital programme set out in notes 4.9 to 4.14 be noted; and
  4. The proposed movement between years set out in paragraph 4.15 to 4.19 be approved.

 

REASON FOR DECISION:

Managing and forecasting capital expenditure effectively was vital in order to support all of the services provided by the Council.

Minutes:

Jane Fineman, Head of Finance and Procurement introduced this Report that summarised the actual and forecast outturn expenditure on capital schemes to 30 September 2019 and included the following:

 

-       Cabinet had approved Capital Expenditure of £22.681m for 2019/20.

-       Since this approval, £1.244m of Projects had been rescheduled from 2018/19 to 2019/20. 

-       Approvals of £28,000 had been made in Quarter 1.  A further £1.7m of expenditure was requested in this Report for 2019/20. 

-       The Report also included the following allocations:

o   £769,000 for beam and concrete repairs to the Royal Victoria Place car park.

o   £520,000 for the purchase of Tonbridge and Malling Waste Bins and Food Caddies – to note, the entire cost would be recharged back to Tonbridge and Malling.

o   £200,000 to deliver interest free loans to lower income families and landlords to enhance energy efficiency in homes.  The loans would be repaid following the sale of the property.

o   £80,000 for CCTV to be installed in Crescent Road, Great Hall and Torrington Road car parks.  All of which were open 24 hours a day.

o   £56,000 for a new Crematorium Management software package.

-       The Report also requested that £4.8m be rescheduled from 2019/20 to 2020/21.

-       In addition the following proposed expenditure had been deferred:

o   £2.962m for the Crescent Road car park extension.

o   £1m for sports sites acquisitions.

o   £588,000 for the building of the Benhall Mill Depot.

o   £120,000 for the Assembly Hall Fire Escape.

o   £44,000 for the resurfacing of the West Station Coach car park

-       Also included in the Report was an additional £1.593m in the budget for 2021 that was approved by Cabinet for the Amelia Scott scheme.

-       The forecast outturn included  the Calverley Square project as the decision to stop the scheme was taken after 30 September 2019.   This would all be reversed out in the Quarter 3 Report.

-       Subject to approval, the total forecast capital spend for 2019/20 would be £20.866m.

 

RESOLVED –

  1. That the actual gross and net expenditure for the year and the sources of finance, as shown in Appendices B to D to the report be noted;
  2. That the proposed variations to the 2019/20 Capital programme set out in paragraphs 4.3 to 4.8 of the report be approved;
  3. That the inclusion of new schemes to the Capital programme set out in notes 4.9 to 4.14 be noted; and
  4. The proposed movement between years set out in paragraph 4.15 to 4.19 be approved.

 

 

 

REASON FOR DECISION:

Managing and forecasting capital expenditure effectively was vital in order to support all of the services provided by the Council.


Meeting: 12/11/2019 - Finance and Governance Cabinet Advisory Board (Item 66)

66 Capital Management Report: Quarter 2 pdf icon PDF 190 KB

To consider and provide a recommendation to Cabinet on the proposals set out in the attached report.

Additional documents:

Minutes:

Jane Fineman, Head of Finance and Procurement introduced this Report that summarised the actual and forecast outturn expenditure on capital schemes to 30 September 2019 and included the following:

 

-       Cabinet had previously approved Capital Expenditure of £22.681m for 2019/20.

-       Since this approval £1.244m of Projects had been rescheduled from 2018/19 to 2019/20 and approvals of £28,000 were made in Quarter 1. £1.7m of expenditure was requested in this report for 2019/20. 

-       In addition the following allocations had been made:

o   £769,000 for beam and concrete repairs to the Royal Victoria Place car park;

o   £520,000 for the purchase of Tonbridge and Malling Waste Bins and Food Caddies (with the entire cost to be recharged back to Tonbridge and Malling);

o   £200,000 to deliver interest free loans to lower income families and landlords for better energy efficiency.  The loans would be repaid when the property was sold.

o   £80,000 for CCTV to be installed in the Crescent Road, Great Hall and Torrington Road car parks; and

o   £56,000 for a new Crematorium Management Software Package.

-       The Report also requested that £4.8m be rescheduled from 2019/20 to 2020/21.

-       In addition the following proposed expenditure had been deferred:

o   £2.962m for the Crescent Road car park extension;

o   £1m for sports sites acquisitions;

o   £588,000 for the building of the Benhall Mill Depot;

o   £120,000 for the Assembly Hall Fire Escape; and

o   £44,000 for the resurfacing of the West Station Coach Park

-       The Report also included an additional £1.593m in the budget for 2021 that was approved by Cabinet for the Amelia Scott Development.

-       To note that the forecast outturn in the Report still included the Calverley Square project as the decision to stop the scheme was taken after 30 September 2019.

-       Subject to approval, the total forecast capital spend for 2019/20 would be £20.866m.

 

Discussion and responses to the member questions included the following:

 

-       A decision on the extension of the Crescent Road car park was due to be submitted to Cabinet in due course, but as no decision had yet been taken the allocated funding would remain in the Capital Plan.

 

RESOLVED – That the recommendations to Cabinet set out in the report be supported.